At the end of November, the final two modules for the P-74 FPSO left Aibel's yard in Thailand.

Modules M8 (Removal System Module) and M9 (PIG Launchers/Receivers and Production & Injection Manifolds Module) are the final two of a total of five modules Aibel is delivering to Estaleiro do Brasil Ltda. (EBR) in the P-74 project. The modules are to be installed on the P-74 FPSO, which is currently under construction at the Brazilian yard Sao Jose do Norte. 

Removal System Module
Module M8 (Removal System Module) is transported from the assembly area (all images: Piyawat Hirunwattanasuk). 

PIG Launchers/Receivers and Production & Injection Manifolds Module
Module M9 (PIG Launchers/Receivers and Production & Injection Manifolds Module) is on its way to the transportation vessel.

"We have successfully delivered five modules to our client EBR. Since the first cut was made in the autumn of 2013, more than 4 million man-hours have been completed. All parties involved have put in a great effort, completing the work with a high degree of safety and quality," says Project Manager Thanakorn Wankanapol. 

At the end of November, the final two modules for the P-74 FPSO left Aibel's yard in Thailand.
The modules have been sea fastened – all set for departure. 

The second and final P-74 delivery had a weight of 4,483 tonnes. The total weight of all five modules was right above 7,000 tonnes. Aibel has been responsible for both procurement and construction. At its peak, the project engaged up to 850 employees in Thailand. 

At the end of November 2015, the final two modules for the P-74 FPSO left Aibel's yard in Thailand.
The modules left the yard early in the morning on 22 November. 


The P-74 modules

 

MODULE

WEIGHT

MEASUREMENTS

 Flare System Module

M01, Flare System Module

1,015 tonnes

W 20 m X L 22 m x H 20 m

 Removal System Module

M8, Removal System Module

1,709 tonnes

W 22 m X L 30 m x H 22 m

 Pig Launchers/Receivers and Production & Injection Manifolds Module

M9, Pig Launchers/Receivers and Production & Injection Manifolds Module

2,774 tonnes

W 27 m X L 22 m x H 23 m

 Chemical Unit and Products Storage

M14, Chemical Unit and Products Storage

705 tonnes

W 22 m X L 13 m x H 20 m

 Utilities module

M15, Utilities

822 tonnes

W 22 m X L 18 m x H 26 m