• From drawing board to fabrication yard

    Aibel undertakes quality work at its own facilities

Ivar Aasen

In November 2013 Aibel was awarded the contract for hook-up of the Ivar Aasen platform. This is Aibel's first assignment for Aker BP (previously Det norske).

Ivar Aasen

The platform deck, which is built by SMOE in Singapore, arrived to the field in July 2016. Aibel's main job started in August, following the lifting campaign.

Aibel is responsible for all hook-up activities. The contract comprises management, administration, engineering, prefabrication and installation work.

The project, which engages up to 400 employees, is carried out in close collaboration with operator Aker BP and Norisol, which is responsible for all ISO work. Following a hectic autumn, the first oil was produced on the platform on 24 December 2016.

Aker BP and Aibel have also signed an agreement for maintenance, modifications and operational support on Ivar Aasen.

News archive

Facts

Ivar Aasen was installed at the field in the North Sea during the summer of 2016.

The topside is built by SMOE in Singapore. The steel jacket is built by Saipem in Sardinia, while the living quarters are constructed by Apply Leirvik at Stord.

The hook-up project is managed from Aibel’s office in Haugesund.