Aibel’s claims are based on additional work and costs incurred by Aibel in order to complete the project in line with the customer's requirements. The claims have been thoroughly prepared and supported by external legal counsel. Seatrium has submitted counterclaims, which Aibel is reviewing as part of the agreed dispute process.
As the dispute has reached a deadlock at the consortium level, the matter now moves into formal arbitration. The matter will be resolved by arbitration under the SCC rules in Stockholm.
This is a standard and contractually defined mechanism for resolving disagreements between the partners. Aibel will continue to follow the established procedures and will address the claims through the arbitration process.
Aibel remains committed to the DolWin 5 project and to supporting its progress toward final completion.
Published 22 January 2026